← BAC Calculator
Budget at Completion Calculator April 2026 · 6 min read

What is Budget at Completion (BAC)?

Budget at Completion (BAC) is the total approved budget for all project work, established as a fixed baseline before execution begins. Per PMBOK 6th Edition (p.263), BAC equals the sum of all budgets for the work to be performed. It is the financial anchor of Earned Value Management — the number against which all cost and schedule performance is measured.

PMBOK Definition of BAC

The Project Management Body of Knowledge (PMBOK® Guide, 6th Edition) defines BAC as:

BAC = The sum of all budgets established for the work to be performed on a project

Critically, BAC is fixed at project baseline. It does not change when cost overruns occur — that would be reflected in Estimate at Completion (EAC). BAC only changes through a formal re-baselining process when the approved scope of work changes fundamentally.

BAC vs Cost Baseline vs Project Budget

TermIncludesChanges?
Project BudgetBAC + Management ReserveOnly via formal change control
Cost Baseline (BAC)All work packages + Contingency ReserveOnly via re-baselining
EACForecast of actual total costUpdated regularly during execution

5 BAC Estimation Techniques

1. Bottom-Up Estimation (Most Accurate)

Estimate each work package individually and sum them. Accuracy: ±5–10%. Best when detailed scope is available. Use our BAC Builder to do this automatically.

2. Analogous Estimation

Use actual costs from similar past projects. Accuracy: ±25–75%. Best for early project stages when detail is limited. Fast but relies on comparable historical data.

3. Parametric Estimation

Use statistical relationships between variables (e.g., cost per square metre, cost per software function point). Accuracy: ±10–20%. Best when reliable historical data exists.

4. Three-Point Estimation (PERT)

Formula: BAC = (Optimistic + 4 × Most Likely + Pessimistic) / 6. Accounts for uncertainty. Produces a more statistically valid estimate than single-point estimates.

5. Expert Judgement

Consult subject matter experts when historical data is unavailable. Often combined with other techniques. Accuracy highly dependent on expert experience.

Real Construction Example

Cost CategoryBudget
Labour & Workforce$400,000
Materials & Supplies$250,000
Subcontractors$200,000
Equipment Rental$100,000
Contingency Reserve (10%)$95,000
BAC (Cost Baseline)$1,045,000
Management Reserve$55,000
Total Project Budget$1,100,000

Common BAC Pitfalls

BAC, EAC, and VAC — Key Relationships

MetricFormulaMeaning
BACFixed at baselineWhat we planned to spend
EACBAC / CPI (most common)What we now forecast to spend
VACBAC − EACProjected surplus (+) or overrun (−)
→ Open the Free BAC Calculator